Timing the Motor Controller

In Chapter 5, the control task was released every 2 ms and had 1 ms to compute and publish a command.

images/04-communication/hardware-loop.svg
Motor-control loop with feedback from the plant to the controller

The control job needs at most 0.55 ms of CPU time. We must bound what happens when other work shares that CPU.

Workload and Analysis Assumptions

A timing claim applies to a specific workload, platform and scheduling policy.

Initially Consequence
One processor The available CPU time in an interval is its length.
Independent jobs Releases are given by the workload. Jobs need no lock and wait for no input after release.
Given execution-time bounds Each job can require its full bound.
Ideal dispatch Scheduler and switch costs are omitted in the initial model.

Make each assumption explicit before using a test.

Learning Objectives

  • Construct and check schedules for independent jobs.
  • Use processor demand and response-time analysis for recurrent tasks.
  • Explain how a server controls interference from event-driven work.
  • Trace a conflicting access, use a mutex and identify a deadlock.
  • Explain how a resource protocol gives a blocking bound for the timing analysis.

Follow a timing requirement from the schedule to the proof obligation.

Release Times, Preemption and Priority

What changes when we move from a one-off job list to a real-time controller?

Question Cases we will use
When does work become ready? One common release, different job-specific releases, or recurrent releases with a period or minimum separation.
Can another job take over? Nonpreemptive jobs keep the CPU until they finish in this model. Preemptive jobs may be interrupted and resumed.
How is ready work ranked? Fixed task priorities in RM and DM. Job priorities based on absolute deadlines in EDF.

Specify the release model, preemption rule and priority rule separately.

Chapter Map: Scheduling Policies

6.1 Scheduling PoliciesRM, DM and EDF on the same workloads
6.2 EDF SchedulabilityUtilization, short deadlines and interval demand
6.3 Fixed-Priority AnalysisCritical instant and response-time iteration
6.4 Irregular Events and ServersService budgets and replenishment
6.5 Concurrency and Shared ResourcesMutual exclusion, deadlock and blocking

From Tasks to Recurring Jobs

For task \(\tau_i\) and its \(k\)th job \(J_{i,k}\), recall the three timing parameters.

Parameter Meaning
\(C_i\) Maximum CPU time of each job
\(T_i\) Exact period for periodic releases, minimum separation for sporadic releases
\(D_i\) Relative deadline, so \(d_{i,k}=r_{i,k}+D_i\)

Implicit deadline: \(D_i=T_i\). Constrained deadline: \(D_i\le T_i\).

A sporadic guarantee covers every release sequence consistent with its minimum separation.

Fixed Priorities on a Ready Queue

The OSEK tasks in Chapter 5 had configured priorities. When their jobs become ready, the scheduler uses that order.

images/06-scheduling/fp-dispatch.svg
At the same time, jobs of control, telemetry and logging are ready. The dispatcher runs the control job with the highest priority.

A ready job uses its task’s assigned priority \(P_i\). The scheduler selects the highest-priority ready job.

Rate Monotonic and Deadline Monotonic

Two tasks have different periods and relative deadlines. Which task receives higher priority?

Task Period \(T_i\) Relative deadline \(D_i\)
A 4 ms 4 ms
B 6 ms 2 ms
Assignment Rule Higher priority here
Rate Monotonic (RM) Shorter period first A
Deadline Monotonic (DM) Shorter relative deadline first B

With implicit deadlines, \(D_i=T_i\), the two rankings coincide.

The Priority Rule Can Decide Feasibility

A and B both release a job at time 0. A needs 1.5 ms of CPU time and B needs 1.0 ms. Recall \(T_A=4\), \(D_A=4\), \(T_B=6\) and \(D_B=2\) ms.

Assignment CPU order after release First response times
RM A, then B \(R_A=1.5\) ms and \(R_B=2.5\) ms. B misses.
DM B, then A \(R_B=1.0\) ms and \(R_A=2.5\) ms. Both meet their deadlines.

When a longer-period task has a tighter deadline, DM can give it the higher priority.

Independent tasks on one preemptive CPU, no overhead. For this example the synchronous releases are the critical instant.

EDF on the Same Job Releases

How would Earliest Deadline First (EDF) schedule the same releases of A and B?

\(A_k\) and \(B_k\) denote the \(k\)th jobs of tasks A and B.

images/06-scheduling/fp-compare-rm-dm-edf.svg
On the same releases, RM runs A first. DM and EDF run B first, and B finishes by its deadline at 2 ms.

EDF chooses the ready job with the earliest absolute deadline. Here that is \(B_1\), due at 2 ms.

When Both Strict Fixed Orders Miss

Two tasks release recurrent jobs with implicit deadlines. For \((T,C,D)\) in ms, \(A=(5,2,5)\) and \(B=(7,4,7)\).

images/06-scheduling/fp-both-orders-and-edf.svg
Fixed A over B misses B1’s deadline at 7; fixed B over A misses A1’s deadline at 5. In this EDF trace A1 finishes at 2, B1 at 6 and A2 at 8.

At 5 ms, EDF lets B finish first: its pending job is due at 7 ms, the newly released A job at 10 ms.

Distinct task priorities in the fixed-priority cases. Synchronous releases on one fully preemptive CPU. A guarantee under EDF follows in the next section.

Nonpreemptive EDF Can Choose the Wrong Job

Each job is given as \((r,C,d)\) (release, CPU demand, absolute deadline). \(A=(0,2,4)\), \(B=(0,1,6)\) and urgent job \(U=(1,1,2)\).

images/06-scheduling/edf-nonpreemptive.svg
Nonpreemptive EDF runs A first and misses U’s deadline. A different work-conserving schedule runs B, U, A and meets all deadlines.

Both schedules keep the CPU busy. The earlier deadline at time 0 leads to a later miss when the job cannot be preempted.

Chapter Map: EDF Schedulability

6.1 Scheduling PoliciesRM, DM and EDF on the same workloads
6.2 EDF SchedulabilityUtilization, short deadlines and interval demand
6.3 Fixed-Priority AnalysisCritical instant and response-time iteration
6.4 Irregular Events and ServersService budgets and replenishment
6.5 Concurrency and Shared ResourcesMutual exclusion, deadlock and blocking

Implicit Deadlines: An Exact EDF Test

Independent recurrent tasks with \(D_i=T_i\) on one preemptive EDF CPU.

\[ U=\sum_i U_i\ \le\ 1 \quad \Longleftrightarrow \quad \text{all deadlines are guaranteed.} \]

Why CPU time
Long-run necessity Jobs released every \(T_i\) require a CPU share of \(U_i=C_i/T_i\).
Interval sufficiency Every job with both endpoints inside an interval occupies \(T_i\) of its task’s release-to-deadline span. These spans do not overlap for the same task.

With implicit deadlines, the utilization bound also controls demand in each interval.

For tasks A and B, \(U=2/5+4/7=34/35<1\). Liu and Layland (1973) for periodic tasks.

Short Deadlines Can Overload a Short Interval

Both tasks have \((C_i,T_i,D_i)=(1,4,1)\). Their combined utilization is \(U=0.5\).

images/06-scheduling/edf-short-interval.svg
Both tasks release jobs at time zero with deadlines at time one. Both jobs must finish in the highlighted first unit of time.

At a simultaneous release, \([0,1]\) needs 2 units of CPU time and offers 1.

The EDF Interval Test

On one preemptive CPU, consider a finite set of independent jobs \(J_k\). Each has release \(r_k\), CPU demand \(C_k\) and absolute deadline \(d_k\).

A job with \(r_k\ge a\) and \(d_k\le b\) must receive all its CPU time in \([a,b]\).

\[ \sum_{k:\ r_k\ge a,\ d_k\le b} C_k\ \le\ b-a \]

Check pairs with \(a\) a release, \(b\) a deadline, and \(a\le b\).

A failing interval proves overload. For this model, EDF meets all deadlines exactly when every interval passes.

Find the Overloaded Interval

Four one-off jobs have the release and deadline windows shown below. Is the total demand of 7 enough to detect an overload?

images/06-scheduling/edf-interval.svg
Four job windows. Only J2 and J4 are entirely inside the interval from 1 to 3. Their CPU demands are 1 and 2.

\(J_2\) and \(J_4\) need 3 units of CPU time in the 2 units available from 1 to 3.

Demand Bound: Count Complete Job Windows

One sporadic task has \(T_i=5\), \(D_i=2\) and \(C_i=1\). Here \(J_k\) abbreviates \(J_{i,k}\) for this task.

images/06-scheduling/edf-job-count.svg
An interval of length 12 contains job windows from time 0 to 2, 5 to 7 and 10 to 12.

The first job needs \(D_i\) from release to deadline. Each additional complete window needs another \(T_i\) units of interval length.

In length 12 there is space for three complete job windows. Their demand is 3.

EDF Tests Processor Demand at Every Length

Maximum CPU demand of one sporadic task in an interval of length \(\ell\):

\[ \operatorname{dbf}_i(\ell) =C_i\max\left(0,\left\lfloor\frac{\ell-D_i}{T_i}\right\rfloor+1\right). \]

Preemptive EDF guarantees the deadlines exactly when \(\sum_i\operatorname{dbf}_i(\ell)\le\ell\) for every \(\ell>0\).

For the two tasks on S19, \(\operatorname{dbf}_1(1)=\operatorname{dbf}_2(1)=1\). The length-1 interval fails.

Independent sporadic tasks with \(0<D_i\le T_i\) on one fully preemptive CPU. Baruah, Mok and Rosier (1990), doi:10.1109/REAL.1990.128746.

Self Check: Same Utilization, Different Windows

Two independent sporadic tasks each have \(C_i=1\) and \(T_i=4\).

Case Relative deadlines Which test answers the question?
A \(D_1=D_2=4\) Does \(U=0.5\) establish a guarantee?
B \(D_1=D_2=1\) Which interval shows a deadline miss is possible?

Under fixed priorities, we now ask how much higher-priority work can delay one job.

Chapter Map: Fixed-Priority Analysis

6.1 Scheduling PoliciesRM, DM and EDF on the same workloads
6.2 EDF SchedulabilityUtilization, short deadlines and interval demand
6.3 Fixed-Priority AnalysisCritical instant and response-time iteration
6.4 Irregular Events and ServersService budgets and replenishment
6.5 Concurrency and Shared ResourcesMutual exclusion, deadlock and blocking

A Critical Instant for Fixed Priorities

Telemetry is ready. How does the timing of a higher-priority control release affect it?

images/06-scheduling/fp-critical-instant.svg
The control job delays telemetry when their releases coincide. A later control release in the comparison occurs after telemetry has finished.

In the independent constrained-deadline model, analyse a simultaneous release with higher-priority tasks and their earliest subsequent releases.

Counting Higher-Priority Work

While a job of task \(i\) is pending, higher-priority job releases can take CPU time away from it.

images/06-scheduling/fp-count.svg
A half-open interval from zero to w contains control releases at zero and two milliseconds. A release exactly at the right boundary is excluded.

For higher-priority task \(j\), at most \(\lceil w/T_j\rceil\) jobs are released in the synchronous interval \([0,w)\).

Multiply the job count by \(C_j\) to bound task \(j\)’s CPU interference.

Response Time Is a Fixed Point

A longer response time can admit more interference. Compute the response time and the interference together.

\[ w_i^{(0)}=C_i,\qquad w_i^{(q+1)}=C_i+\sum_{j\in hp(i)}\left\lceil\frac{w_i^{(q)}}{T_j}\right\rceil C_j. \]

  • \(w_i^{(q)}\) is the response window for task \(i\) at iteration \(q=0,1,\ldots\).
  • \(j\) ranges over \(hp(i)\), the indices of tasks with strictly higher priority than \(i\).
  • Stop at the first unchanged value. It gives \(R_i\) in the critical-instant model.
  • If the estimate exceeds \(D_i\), the test fails.

Compare the worst-case response time \(R_i\) with the relative deadline \(D_i\).

Worked Example: Control, Telemetry and Logging

The motor controller shares its CPU with two lower-priority tasks. Verify the logging deadline.

Task, highest priority first \(T_i\) \(C_i\) \(D_i\)
Control 2 ms 0.55 ms 1.0 ms
Telemetry 5 ms 0.70 ms 2.1 ms
Logging 10 ms 0.80 ms 4.0 ms

Logging iteration in ms: \(0.80 \to 2.05 \to 2.60 \to 2.60\).

Logging admits a second release of control. Its response time is 2.60 ms.

A Quick Sufficient Test for RM

A utilization check for \(n\) tasks can prove schedulability without iterating the response times.

\[ U=\sum_{i=1}^{n}\frac{C_i}{T_i} \;\le\; n\left(2^{1/n}-1\right). \]

Implicit-deadline example under RM Result
\((T_i,C_i)=(4,1),(5,2),(20,5)\) \(U=0.90\) exceeds the three-task bound of about \(0.78\).
Exact response times in the synchronous model \((1,3,15)\). All three deadlines are met.

When the sufficient bound fails, use a more precise test.

An Exact RM Test for Harmonic Periods

Sort the tasks by period. The periods are harmonic if each period is an integer multiple of the preceding one. For example, \(2,6,12\) are harmonic.

For independent periodic tasks with \(D_i=T_i\) on one preemptive CPU, RM meets all deadlines if and only if \(U\le1\) when the periods are harmonic.

At the critical instant, each higher-priority task \(j\) releases exactly \(T_i/T_j\) jobs in \([0,T_i)\). The CPU demand for the first job of task \(i\) and its higher-priority work is

\[ C_i+\sum_{j\in hp(i)}\frac{T_i}{T_j}C_j =T_i\left(U_i+\sum_{j\in hp(i)}U_j\right)\le T_i \qquad\text{if } U\le1. \]

Use a fixed tie-break for equal periods. The analysis assumes zero scheduling overhead.

Harmonic RM at Full Utilization

The tasks release together at time 0, with \(D_i=T_i\). Time is in ms.

Task in RM order Period \(T_i\) CPU demand \(C_i\) Jobs released in \([0,12)\) CPU time in that window
\(\tau_1\) 2 1 6 6
\(\tau_2\) 6 2 2 4
\(\tau_3\) 12 2 1 2

\(U=1/2+2/6+2/12=1\). The periods form a harmonic chain, so RM guarantees all three deadlines.

Self check. Would the exact harmonic test still apply to periods \(4,6,12\)?

Chapter Map: Irregular Events and Servers

6.1 Scheduling PoliciesRM, DM and EDF on the same workloads
6.2 EDF SchedulabilityUtilization, short deadlines and interval demand
6.3 Fixed-Priority AnalysisCritical instant and response-time iteration
6.4 Irregular Events and ServersService budgets and replenishment
6.5 Concurrency and Shared ResourcesMutual exclusion, deadlock and blocking

A Diagnostic Event Delays Control

A motor-control job and a high-priority diagnostic job are released together at \(t=0\).

images/06-scheduling/server-missed-deadline.svg
Diagnosis runs for 0.50 ms. The controller then runs for 0.55 ms and finishes after its deadline at 1.00 ms.

One diagnostic job can consume more than the controller’s 0.45 ms of timing margin.

Arrival Bounds and Admission

What can we promise when diagnostics arrive at irregular times?

Available assumption Scheduling implication
A guaranteed minimum gap \(T_i\) and known \(C_i,D_i\) Include the sporadic task in the analysis at design time.
An extra job requests a guaranteed deadline at runtime Admit the job if its deadline and existing commitments can be met.
Service requests need responsive best-effort handling Queue them for budgeted service and specify what happens on overload.

The arrival model bounds incoming demand. Admission determines which extra deadlines the system promises.

Budgeted Diagnostic Service

A diagnostic interrupt can arrive at any point in the controller’s execution.

images/06-scheduling/server-service-path.svg
A short interrupt handler enqueues a request. The server can dequeue and execute work while it has CPU budget.
Parameter Meaning
\(Q_s\) Budget of server \(s\), measured in CPU time
\(T_s\) Period of polling or fixed replenishment, or replenishment delay for the Sporadic Server

Keep IRQ work short and account for it separately. The server limits scheduled diagnostic CPU work.

Background Service

A diagnostic request arrives at 0.10 ms and needs 0.20 ms of CPU time. The control job released at 0 needs 0.55 ms.

images/06-scheduling/server-background.svg
Control runs until 0.55 ms. The waiting diagnostic request then runs from 0.55 to 0.75 ms.

Background service uses otherwise idle CPU time. Its delay depends on how long higher-priority work keeps the CPU busy.

Polling Server

Can a periodic service limit the impact of diagnostics? Use \(Q_s=0.25\) ms and \(T_s=2\) ms at a priority above control.

images/06-scheduling/server-polling.svg
The poll at time zero finds an empty queue. The request released at 0.10 ms runs from 2.00 to 2.20 ms.

An empty poll gives up the budget. A request just after that poll waits for the next server release.

Deferrable Server

The polling server gave up its budget just before the request arrived. Keep \(Q_s=0.25\) ms available within each 2 ms period.

images/06-scheduling/server-deferrable.svg
The request starts at 0.10 ms and finishes at 0.30 ms. Control resumes and completes at 0.75 ms.

Retain unused budget until the end of the period. A ready request can use it immediately at the server’s priority.

Deferrable Server Interference

A larger request needs 0.50 ms and arrives at 1.75 ms. The server has used none of its initial 0.25 ms budget.

images/06-scheduling/server-double-hit.svg
The deferrable server runs for 0.25 ms just before and 0.25 ms just after the fixed replenishment at 2.00 ms.

A short window straddling a replenishment can contain two full budgets.

Sporadic Server Replenishment

Can the server keep unused budget and avoid refilling it at a fixed boundary?

images/06-scheduling/server-sporadic.svg
The sporadic server spends 0.25 ms starting at 1.75 ms. That budget is restored at 3.75 ms, when the remaining diagnosis starts.

Link replenishment to budget use. In this trace the spent 0.25 ms becomes available at \(1.75+2.00=3.75\) ms.

Four Service Policies on One Trace

Compare the same 0.20 ms request released at 0.10 ms under each policy.

Service When the queue is empty Diagnosis starts First control job finishes
Background No CPU work 0.55 ms 0.55 ms
Polling Server Ends the current poll 2.00 ms 0.55 ms
Deferrable Server Keeps budget within the period 0.10 ms 0.75 ms
Sporadic Server Keeps available budget 0.10 ms 0.75 ms

The first request can see the same service from two servers while their later interference differs.

The Controller’s Bound with a Server

The controller needs 0.55 ms of CPU time by its 1.00 ms deadline. Interrupt and scheduler overhead uses at most 0.05 ms in that window.

\[ \underbrace{0.55\,\mathrm{ms}}_{\text{control}} + \underbrace{0.25\,\mathrm{ms}}_{\text{server}} + \underbrace{0.05\,\mathrm{ms}}_{\text{overhead}} = 0.85\,\mathrm{ms} \]

The calculation assumes that the selected server contributes at most 0.25 ms within the controller’s 1.00 ms response window.

The server’s interference bound enters the same response-time argument as higher-priority task execution.

CPU Time and Shared State

A sample record stores a speed value and a timestamp. One software task publishes it, and control reads it.

  • How much CPU time can other work take from control in the next millisecond?
  • What can control read if it preempts the writer between two stores?

The CPU budget bounds competition for execution time. A shared record also needs a rule for concurrent access.

Chapter Map: Concurrency and Shared Resources

6.1 Scheduling PoliciesRM, DM and EDF on the same workloads
6.2 EDF SchedulabilityUtilization, short deadlines and interval demand
6.3 Fixed-Priority AnalysisCritical instant and response-time iteration
6.4 Irregular Events and ServersService budgets and replenishment
6.5 Concurrency and Shared ResourcesMutual exclusion, deadlock and blocking

Resources That Jobs Share

The producer publishes sensor samples. Control reads them. Telemetry may also use the same driver.

Resource What must be coordinated?
CPU Which ready job executes now?
Sample buffer Can the reader see an update in progress?
Peripheral or driver state Can two jobs have overlapping operations on the same device?

A shared resource is something multiple jobs need. Its access rules depend on what they do with it.

One CPU, an Inconsistent Sample

A sensor record pairs sample \(s\) with timestamp \(t\). In this trace, subscripts 0 and 1 mark the old and new versions.

images/06-scheduling/resource-interleaving.svg
The low-priority producer writes a new sample and is preempted. Control reads the new sample with the old timestamp.

Preemption can expose an incomplete update, even if individual reads and writes are atomic.

A Mutex Protects the Pair

Both jobs must use the same lock around their access to the sample buffer.

Producer Controller
Lock the buffer mutex. Lock the buffer mutex.
Write sample and timestamp. Read sample and timestamp into local variables.
Unlock the buffer mutex. Unlock the buffer mutex.

A critical section is the protected code. A mutex admits one owner at a time.

Direct Blocking by the Owner

Control needs the sample mutex. The lower-priority producer already owns it.

images/06-scheduling/resource-direct.svg
Control waits at time 1, the owner unlocks at time 3, and control then runs.

The controller is blocked on a lock until the owner releases it.

The trace omits lock-call and dispatch costs. H and L denote high and low priority.

Priority Inversion Can Extend the Wait

A medium-priority job becomes ready while the controller waits for the mutex owner.

images/06-scheduling/resource-inversion.svg
The medium-priority job displaces the lock owner from time 2 to 5, extending the controller’s wait to time 6.

The medium-priority job delays the controller indirectly: it preempts the owner that must release the lock.

Deadlock Is a Cycle of Waiting

Two jobs each own one lock and request the other lock before releasing their own.

images/06-scheduling/resource-deadlock.svg
Wait-for cycle: A holds S and waits for Q; B holds Q and waits for S.

In this deadlock, neither job can progress to its unlock, even if the CPU is available.

Use One Order for Nested Locks

Require every job that needs both locks to acquire the sample lock S before the diagnostic lock Q.

Allowed Rejected by the locking rule
Lock S, then lock Q. Lock Q, then request S while holding Q.
Release Q, then release S. Introduce a dependency that contradicts the global order.

A global lock order prevents circular wait among locks that follow the rule.

Priority Inheritance Lets the Owner Run

A high-priority job blocks on a mutex. The owner temporarily inherits the blocked job’s priority.

images/06-scheduling/resource-inheritance.svg
With priority inheritance, the owner runs until time 3, control runs next, and medium-priority work is delayed until time 4.

The Priority Inheritance Protocol (PIP) lets the owner finish before the medium-priority job can delay the release.

What Priority Inheritance Leaves Open

A mutex owner may itself be blocked while it holds another lock.

Situation What priority inheritance changes
H waits for L, and L waits for a third owner. The inherited priority propagates along the wait chain.
A job meets more than one contested critical section. Its total blocking can include several critical sections.
A set of jobs wait in a cycle. Raising priorities leaves every participant waiting.

PIP limits preemption of lock owners. The lock structure still determines how many delays can accumulate.

Set Each Resource’s Priority Ceiling

Control, telemetry and the logger run at fixed priorities, in that order from highest to lowest.

Resource Configured users Resource ceiling
Sample lock S Control and logger Control’s priority
Diagnostic lock Q Telemetry and logger Telemetry’s priority

A resource’s priority ceiling is the highest base priority of any job that may acquire it.

Original PCP Also Checks Free Locks

The logger holds S. Telemetry preempts the logger and requests Q, which is free.

  1. S is held by another job. Its ceiling is Control’s priority.
  2. Telemetry’s effective priority does not exceed that ceiling. The request for Q waits.
  3. The logger inherits Telemetry’s priority. It can finish the critical section and release S.

Original Priority Ceiling Protocol (O-PCP) admits a free lock only when the requester’s effective priority exceeds the ceilings of all locks held by other jobs.

OSEK Raises Priority at Lock Acquisition

In a correctly configured OSEK task-only example, the logger calls GetResource(S).

Protocol When does the logger’s priority rise?
Original PCP When a requester actually blocks because of the held lock or its ceiling.
OSEK ceiling rule As soon as the logger acquires S, up to the resource ceiling if that is higher.

With the immediate priority raise, Control may stay Ready while the logger completes its critical section.

Bound the Blocking Term Under Original PCP

On one CPU under Original PCP, one lower-priority critical section can contribute to a job’s blocking bound.

Find the candidates for \(B_i\) Test
Who may hold the lock? A task with lower base priority than task \(i\).
Which lock counts? Its ceiling is at least as high as task \(i\)’s base priority.
How much time? Take the longest CPU execution bound of the qualifying critical sections. Use zero if none qualify.

The blocking bound \(B_i\) can include a resource that task \(i\) never accesses, through the ceiling rule.

Blocking Bounds for Control and Telemetry

Control outranks Telemetry, which outranks the logger. In this example, the logger is the only lower-priority task that can hold a qualifying lock for either task.

Logger’s critical section Ceiling CPU time bound Can block Control? Can block Telemetry?
Update sample S Control 0.20 ms Yes Yes
Update diagnostic buffer Q Telemetry 0.30 ms No Yes

\(B_{\mathrm{Control}}=0.20\,\mathrm{ms}\) and \(B_{\mathrm{Telemetry}}=0.30\,\mathrm{ms}\) under Original PCP.

The two logger sections are disjoint and included in its CPU demand of 0.80 ms per job.

Add Blocking to Response-Time Analysis

For fixed priorities on one CPU, extend the response-time recurrence from earlier in the chapter.

\[ w_i^{(0)}=C_i+B_i,\qquad w_i^{(q+1)}=C_i+B_i+\sum_{j\in hp(i)} \left\lceil\frac{w_i^{(q)}}{T_j}\right\rceil C_j. \]

Task Iteration in ms Deadline check
Control \(0.55+0.20=0.75\) with no higher-priority interference \(0.75\le1.00\)
Telemetry \(0.70+0.30=1.00\;\to\;1.00+\lceil1.00/2\rceil\,0.55=1.55\;\to\;1.55\) \(1.55\le2.10\)

Both deadlines are verified with a bound for lower-priority blocking and higher-priority interference.

Constrained relative deadlines, no release jitter, and no other suspension. Ignore dispatch and lock overhead in this teaching example.

Diagnose a Delay Before Choosing a Protocol

For each trace, explain who holds which resource and which job can still advance.

Observation Question to ask
Control waits for the sample lock. Can the owner run and release it?
A medium-priority job runs while the owner is ready. Which priority does scheduling use for the owner?
Two owners wait for each other’s locks. Which rule could prevent the cycle?

Separate direct blocking, extended priority inversion and deadlock. A timing proof needs a bound for the delays that remain.

EZS Cheat Sheet · Tasks and Jobs

\(i\) identifies a task. \(k=1,2,\ldots\) counts its successive jobs.

Task notation Meaning Job notation Meaning
\(\tau_i\) Task \(i\) \(J_{i,k}\) Job \(k\) of task \(i\)
\(T_i\) Period or minimum inter-arrival time \(r_{i,k}\) Release time
\(C_i\) Execution-time bound per job \(d_{i,k}=r_{i,k}+D_i\) Absolute deadline
\(D_i\) Relative deadline \(f_{i,k}\) Finish time
\(\phi_i\) Phase of a periodic task \(f_{i,k}-r_{i,k}\) Actual response time
\(J_i\) Release jitter bound \(f_{i,k}\le d_{i,k}\) Deadline met
\(R_i\) Worst-case response time

Periodic \(\tau_i=(T_i,C_i,D_i,\phi_i)\) · Sporadic \(\tau_i=(T_i,C_i,D_i)\)

Burns Standard Notation (Davis, 2013). Course conventions \(\phi_i\), \(J_{i,k}\), \(r_{i,k}\) and \(f_{i,k}\).

EZS Cheat Sheet · Scheduling Analysis

\(i\) identifies the analysed task and \(j\) a higher-priority task. \(q\) counts the iteration steps from 0. \(s\) identifies a server.

Symbol Meaning
\(n\), \(U_i\), \(U\) Number of tasks, task utilization \(U_i=C_i/T_i\), total utilization \(U=\sum_i U_i\)
\(P_i\), \(hp(i)\) Base priority of task \(i\), indices of tasks with strictly higher priority
\(\ell\), \(\operatorname{dbf}_i(\ell)\) Window length, maximum CPU demand of task \(i\) from jobs released and due within it
\(w\), \(w_i^{(q)}\) Response-window length, its estimate for task \(i\) at iteration \(q\)
\(B_i\), \(R_i\) Lower-priority blocking bound, worst-case response time
\(Q_s\), \(T_s\) Server budget in CPU time, replenishment period or delay
\(C_s=Q_s\) Execution-time bound when modelling a polling server as a periodic task

Burns Standard Notation (Davis, 2013). Course conventions \(\operatorname{dbf}_i(\ell)\), \(w_i^{(q)}\), \(Q_s\) and \(T_s\).

EZS Cheat Sheet · Finite Job Sets and Trace Labels

Symbol Meaning
\(J_k\) Job \(k\) in a finite set of independent jobs
\(r_k\), \(C_k\), \(d_k\), \(f_k\) Release time, CPU demand, absolute deadline, finish time of \(J_k\)
\([a,b]\) Test interval from release \(a\) to deadline \(b\), with length \(b-a\)
\(L_k=f_k-d_k\), \(L_{\max}=\max_k L_k\) Lateness of \(J_k\), maximum lateness over all jobs

Recurring-job traces. \(A_k\) and \(B_k\) are the \(k\)th jobs of tasks A and B. The demand-bound trace shows \(J_k\) for job \(k\) of its one sporadic task.

Sensor-buffer trace. In \((s_1,t_0)\), \(s\) denotes a sample value and \(t\) a timestamp. Subscripts 0 and 1 mark the old and new measurements.

Self Check: What Delays the Controller?

The control code still needs 0.55 ms of CPU time and has a 1 ms deadline.

Observation Question to answer
A high-priority diagnostic job runs at release. How much higher-priority demand belongs in the response window?
Diagnosis is moved to a server. When can it spend its budget, and when is that budget available again?
The control job needs a protected sample. Which lower-priority critical section can block it? Can its owner reach the unlock?

Identify the source of the delay before choosing the timing model.

From CPU Execution Time to End-to-End Timing

The schedule depends on the execution-time bounds and on where the work runs.

Next question Model to extend
How do we justify \(C_i\)? Analyse execution paths and platform timing in WCET estimation.
What if a job needs another component’s output? Model precedence and communication between activities.
What if work runs on multiple processors or crosses a bus? Map work to resources and connect their timing guarantees.

Carry the assumptions of each local bound into the system-level timing argument.

Appendix: A Finite Set of CPU Jobs

Three one-off jobs \(J_k\) become ready together. A batch of queued operations for one machine has the same structure.

Job Release \(r_k\) CPU demand \(C_k\) Absolute deadline \(d_k\)
\(J_1\) 0 2 4
\(J_2\) 0 1 3
\(J_3\) 0 2 7

With finish time \(f_k\), a job’s lateness is \(L_k=f_k-d_k\). All deadlines are met when \(L_{\max}=\max_k L_k\le 0\).

Each row is a one-off job. Time is in arbitrary units. We schedule on one CPU. Jobs are independent, run without self-suspensions and are charged their stated CPU demand. Dispatch and preemption overhead are zero in this model.

Appendix: Earliest Due Date with a Common Release

At time 0 all three jobs are ready. Earliest Due Date (EDD) runs them in increasing order of absolute deadline.

images/06-scheduling/edf-edd.svg
First order J1, J3, J2 with maximum lateness 2. EDD order J2, J1, J3 with maximum lateness minus 1.

With a common release, all jobs are known at the start. One sort by deadline gives an optimal order for maximum lateness.

Appendix: The EDD Exchange Argument

Suppose adjacent jobs run in the order \(B,A\) even though \(d_A\le d_B\).

Ending times What the swap to \(A,B\) changes
\(A\) moves earlier Its lateness cannot increase.
\(B\) ends at the old finish time of \(A\) Its lateness is at most the old lateness of \(A\), since \(d_B\ge d_A\).
The pair takes the same total time The other jobs keep their finish times.

Eliminate each inverted pair without increasing \(L_{\max}\). EDD minimizes maximum lateness.

Appendix: The EDD Deadline Prefix Test

With all jobs released at time 0, every job with \(d_k\le b\) must fit before deadline \(b\).

\[ \sum_{k:\ d_k\le b} C_k\ \le\ b\qquad\text{for each deadline } b. \]

Deadline \(b\) CPU time due by \(b\) Meets the prefix condition?
3 1 \(1\le 3\)
4 \(1+2=3\) \(3\le 4\)
7 \(1+2+2=5\) \(5\le 7\)

EDD finishes one such prefix after another, so this test is exact.

Appendix: EDF Selects the Earliest Ready Deadline

Controller, diagnosis and logging can become ready at different times. Preemptive Earliest Deadline First (EDF) runs the ready job with the earliest absolute deadline.

images/06-scheduling/edf-preemption.svg
J1 released at 0 with deadline 6, J2 at 1 with deadline 3, J3 at 3 with deadline 8. CPU trace J1, J2, J1, J3 with switches at 1, 2 and 4.

\(J_2\) preempts \(J_1\) at time 1. \(J_3\) waits at time 3 because \(J_1\) still has the earlier deadline.

Appendix: Why EDF Can Repair Any Feasible CPU Plan

At the first disagreement, the current plan runs \(B\). EDF would run \(A\), already ready, with \(d_A\le d_B\).

  1. Move a later slice of \(A\) to this earlier position.
  2. Move the displaced slice of \(B\) to the old position of \(A\).
  3. In a feasible plan that old position ends by \(d_A\le d_B\).

With preemption, the exchange preserves deadlines. If a feasible schedule exists, EDF finds one.

One CPU, finite independent jobs, arbitrary releases, preemption and no dispatch cost. Horn (1974), as presented by Chen A9/12–13.

Appendix: A Nonpreemptive Plan May Need Idle Time

Two jobs remain, given as \((r,C,d)\) (release, CPU demand, absolute deadline). \(A=(0,2,4)\) and urgent job \(U=(1,1,2)\).

images/06-scheduling/edf-deliberate-idle.svg
With B removed, starting A at 0 misses U. An idle slot until 1 lets U run on time, then A runs from 2 to 4.

A plan that knows when \(U\) will arrive can reserve the first short window for it.

Reading Guide

Reading in Marwedel, 4th edition

  • Independent jobs and recurrent tasks → §§6.2.1 and 6.2.3
  • Sporadic events and server motivation → §6.2.5
  • Resource access protocols → §§4.2.1–4.2.4
  • Follow-up on execution bounds → §5.2.2

Marwedel covers the scheduling and locking models. The server papers extend the short introduction in §6.2.5.

References

  • P. Marwedel. Embedded System Design, 4th ed., 2021. Springer
  • R. I. Davis. Burns Standard Notation for real time scheduling, 2013. Author’s copy
  • P. Ulbrich. Echtzeitsysteme (EZS), FAU Erlangen-Nürnberg, winter semester 2019/20. Lecture slides
  • S. Baruah, A. Mok and L. Rosier. Preemptively Scheduling Hard-Real-Time Sporadic Tasks on One Processor, 1990. Paper
  • N. Audsley et al. Applying New Scheduling Theory to Static Priority Pre-emptive Scheduling, 1993. Paper
  • B. Sprunt, L. Sha and J. Lehoczky. Scheduling Sporadic and Aperiodic Events in a Hard Real-Time System, 1989. Technical report
  • L. Sha, R. Rajkumar and J. Lehoczky. Priority Inheritance Protocols, 1990. Paper
  • OSEK/VDX. Operating System Specification 2.2.3, 2005, §8. Specification