Real-Time Operating Systems

Execution Models and Scheduling Foundations · ES/CPSF

Peter Ulbrich

Winter Semester 2026/27
🚀 by Decker

The Motor Controller Has a Timing Contract

The plant moves while software is reading the sensor, computing and updating the output.

images/04-communication/hardware-loop.svg
Motor-control loop with sensor, controller, output interface, actuator and plant

This chapter asks how to run the controller on time.

Learning Objectives

What must we know before we can promise a timely motor update?

  • Obtain the sampling period, software deadline and execution-time bound.
  • Explain what changes from a periodic loop to a schedule table and online selection.
  • Trace a release, a scheduling decision and a context switch.
  • Explain which timing services and isolation an RTOS configuration provides.
  • Model recurring work and individual jobs using Burns notation.

Use the same motor controller for each implementation and for the task model.

Chapter Map: Timing Requirements

5.1 Timing RequirementsFrom plant timing to firmware scheduling
5.2 Scheduling ImplementationsPeriodic loop, schedule table and online selection
5.3 Execution ModelsSwitch points and activation lifecycles
5.4 RTOS Requirements and ArchitectureAUTOSAR, kernel designs, protection and OSEK/VDX
5.5 Task Model and SchedulabilityTask tuples, jobs and timing guarantees

Start with timing requirements that the plant imposes.

The Plant Sets the Sampling Period

The motor speed changes between observations. The controller operates on sampled values.

images/05-rtos/plant-period.svg
Samples on a qualitative motor-speed curve, with a bracket showing the sampling period

The control design selects the sampling period from plant dynamics and the required control quality.

Teaching example: a controller designed and validated for one observation every 2 ms.

The Control Path Sets the Software Deadline

The application requires each command to take effect at the output within 1.5 ms of sampling.

images/05-rtos/deadline-budget.svg
One 1.5 ms end-to-end budget divided into 0.2 ms before release, 1.0 ms for software response and 0.3 ms after software completion

Give the control computation a 1.0 ms relative deadline from the time its sample is ready.

Illustrative allocations for a revised design. The 2 ms sampling period is a separate requirement.

What Happens After a Missed Deadline?

The consequence depends on what the application does with a late result.

images/05-rtos/deadline-consequences.svg
Three panels comparing a hard timing violation, a firm result that expires, and a soft result whose value gradually declines

A hard deadline is a required guarantee. With a firm or soft deadline, specify the acceptable loss or degradation.

The Implementation Sets the WCET Bound

The control step reads the published sample, computes the command and publishes it for output. Some inputs take a longer code path.

What must be fixed or bounded? Motor-control example
Code and inputs Bounded filter work and a saturation branch
Target hardware Processor speed and the memory configuration from Chapter 03
Execution-time bound Assume 0.55 ms of CPU execution per invocation under those conditions

The WCET bound is a demand on CPU time. The deadline limits elapsed time, including any wait for the CPU.

Assumed bound for teaching. Waits and OS overhead are accounted for separately in this example.

Chapter Map: Scheduling Implementations

5.1 Timing RequirementsFrom plant timing to firmware scheduling
5.2 Scheduling ImplementationsPeriodic loop, schedule table and online selection
5.3 Execution ModelsSwitch points and activation lifecycles
5.4 RTOS Requirements and ArchitectureAUTOSAR, kernel designs, protection and OSEK/VDX
5.5 Task Model and SchedulabilityTask tuples, jobs and timing guarantees

Implement the same timing contract with a loop, a table and online selection.

A Timer-Paced Control Loop

Start with one function on the microcontroller. Every sample triggers one control step.

next = first_release_time
forever:
    wait_until(next)
    sample = read_published_sample()
    publish_command(control_step(sample))
    next = next + sampling_period
    if now() > next:
        next = apply_overrun_policy(next)

The timer keeps control releases in phase with sampling, even when the control step takes different amounts of time.

Pseudocode. The sample is available at the illustrated wake-up; the hardware handles acquisition and the output update.

Several Functions Share One Timer

The control function and housekeeping are due at different intervals. Both can be due on the same tick.

images/05-rtos/superloop.svg
Aligned periodic release marks for control and housekeeping on a common timer tick

Counters determine which functions are due. The loop defines their execution order.

Release marks show which functions may run. The diagram omits their execution times.

Move the Plan into a Table

As more functions acquire their own timing constraints, the loop needs more counters and conditions.

Implementation Where is the execution order specified?
Periodic loop with counters In the conditions and order of function calls
Table-driven dispatcher In entries for successive time slots, prepared before execution

The dispatcher enacts the table at runtime.

A Precomputed Dispatch Table

A diagnostic event arrives after the next action has already been fixed in the table.

images/05-rtos/dispatch-table.svg
Precomputed sequence with control, housekeeping and a reserved diagnostic window; the event waits for that window

The reservation gives the request a planned service opportunity.

Schematic example with one pending request and enough time in the reserved window.

When the Ready Work Is Known at Runtime

A diagnostic request can arrive while another function is executing. Each invocation to be scheduled is a job.

Approach Where does the next CPU assignment come from?
Precomputed table At the planned boundary, dispatch the action assigned to this slot.
Online scheduler At a scheduling point, select from the work that is ready using the configured rule.

With online scheduling, the scheduler makes the concrete choice at runtime.

What the Firmware Is Already Managing

The microcontroller runs firmware: software stored on the device that controls its hardware and application.

In the implementation so far What the CPU or system has to do
Periodic loop Check the time and decide which functions are due.
Schedule table Track the current slot and start the planned function.
Online scheduling Record ready work, make a selection and enact it.

These are system-software responsibilities. They can live in the application firmware or be provided by a reusable kernel.

Time spent on bookkeeping, selection or a switch is execution overhead. It is part of the timing budget.

Chapter Map: Execution Models

5.1 Timing RequirementsFrom plant timing to firmware scheduling
5.2 Scheduling ImplementationsPeriodic loop, schedule table and online selection
5.3 Execution ModelsSwitch points and activation lifecycles
5.4 RTOS Requirements and ArchitectureAUTOSAR, kernel designs, protection and OSEK/VDX
5.5 Task Model and SchedulabilityTask tuples, jobs and timing guarantees

Decide when execution can switch and how one invocation is expressed.

Cooperative and Preemptive Execution

An urgent diagnostic request arrives during a control function.

Execution rule When can the CPU switch to another function?
Non-preemptive call At return from the running call.
Cooperative execution At a defined handover, for example when the running code yields or blocks.
Preemptive execution At an allowed scheduling point, even if the running code has not offered to hand over.

The execution rule determines which switch points are allowed. The scheduling policy selects the work.

When Can Another Job Take Over?

An urgent diagnostic job becomes ready while the control job is running.

images/05-rtos/preemption.svg
Same release and deadline under preemptive and non-preemptive execution; the urgent job meets the deadline only in the preemptive trace

Preemption can bring urgent work forward. A cooperative handoff waits for an allowed switch point.

Same jobs in both traces. Scheduler and context-switch costs are omitted here.

Two Lifecycles for the Same Control Step

The control code needs a sample each time. Where does the waiting happen?

Run-to-completion handler

on_control_activation(sample):
    publish_command(control_step(sample))
    return

The runtime calls the handler again for the next activation.

Persistent thread

control_thread():
    forever:
        sample = wait_for_sample()
        publish_command(control_step(sample))

The thread blocks when there is no sample to process.

Lifecycle and preemption are separate choices.

Illustrative pseudocode. The handler executes outside interrupt context.

Ready, Running and Waiting

A control job asks the driver to perform an asynchronous transfer.

images/05-rtos/states.svg
Ready, running and waiting states with transitions for dispatch, preemption, waiting and event notification

A blocked caller frees the CPU. A ready caller can compete for it again.

Four Choices in Scheduling

“Timer-driven”, “online” and “fixed priority” can all describe the same controller.

Choice Examples
What triggers action? Timer expiry or device event
When is the CPU allocation decided? Precomputed table or online selection
When may running work be displaced? Preemptive, non-preemptive or explicit cooperative switch points
How is eligible work ranked? Fixed task priority or a job-dependent rule such as earliest absolute deadline

Read each term as an answer to a different design question.

Chapter Map: RTOS Requirements and Architecture

5.1 Timing RequirementsFrom plant timing to firmware scheduling
5.2 Scheduling ImplementationsPeriodic loop, schedule table and online selection
5.3 Execution ModelsSwitch points and activation lifecycles
5.4 RTOS Requirements and ArchitectureAUTOSAR, kernel designs, protection and OSEK/VDX
5.5 Task Model and SchedulabilityTask tuples, jobs and timing guarantees

Connect the RTOS requirements to concrete execution paths and protection.

What Do We Need from an RTOS?

A reusable kernel takes over timer, event and execution management for the motor controller.

Requirement What we need from the configured system
Predictable timing Bounds on interrupt latency and on the kernel paths we use.
Time and scheduling services A time base, release and wait primitives, and an execution policy that can support the required timing.
Costs that fit the budget Service and dispatch costs low enough for the application’s deadline and load.

An RTOS provides mechanisms for meeting timing requirements. The application still needs a timing argument.

Who Decides, and Who Switches?

A timer or an interrupt makes another job ready. The current context is still on the CPU.

Responsibility Decision or action
Release or wake-up Make the work ready according to the timer or device event.
Scheduler At a scheduling point, apply the policy to decide which context should run and whether it replaces the current one.
Dispatcher Enact that decision by saving and restoring context as required and transferring control.

The scheduler decides. The dispatcher implements the switch that makes preemption possible.

From DMA Completion to the Next CPU Assignment

The device finishes a transfer. Another job is still running.

images/05-rtos/interrupt-path.svg
DMA completion, short ISR, ready interval, scheduling decision and dispatched control job on one time axis

The ISR makes the caller ready. The scheduler selects it at a scheduling point. The dispatcher resumes it.

AUTOSAR Classic Software Layers

Where do motor control, communication stacks and the real-time kernel fit on one electronic control unit (ECU)?

images/05-rtos/autosar-classic.svg
AUTOSAR Classic application software over the RTE, with OS in BSW system services above ECU abstraction, MCAL and hardware

The RTE connects components and BSW services. The OS provides execution services within Basic Software.

Selected layers and examples. Teaching diagram based on AUTOSAR Classic Platform.

Where Do OS Services Run?

Compare three ways to implement the OS services beneath the application interfaces.

images/05-rtos/driver-placement.svg
Library OS with one flat address space and a common CPU mode, monolithic kernel with privileged services, and microkernel with separate user-mode service domains

Moving a service out of the kernel changes which code executes with privilege and how clients reach it.

Three example configurations. Microkernel example: seL4 documentation.

Calls, Protection and Fault Scope

A control function requests a device operation. Which boundary does the request cross?

Example Interface and boundary If the driver writes to the wrong address
Linked OS library Direct function call within the same flat domain The driver can corrupt reachable controller and OS state.
Monolithic kernel System call into a privileged kernel with in-kernel drivers A privileged driver fault can affect kernel state and other clients.
Microkernel Kernel-mediated interprocess communication (IPC) with a user-mode driver The driver’s permissions constrain the write. Clients can still lose the service.

The privileged code and granted access rights determine the fault scope. A boundary also changes the execution path.

Lightweight and Heavyweight Execution Contexts

Control and diagnosis need separate execution contexts. Should they share the same memory and access rights?

Example What changes on a switch? What does the boundary protect?
Lightweight: threads in one process Save and restore registers, program counter and stack pointer. Threads have their own stacks but share the address space and its permissions.
Heavyweight: separate processes Switch execution context and, where applicable, address-space or protection state. Each process has its own access domain. Sharing requires an explicit mapping or IPC.

An execution context holds where the code resumes. A protection domain controls which memory and devices it can reach.

“Lightweight” and “heavyweight” describe the two illustrative cases here.

Memory Management and Stack Protection

A diagnostic thread needs a stack, private state and a controlled way to share samples.

Mechanism What it does Example
Memory management Allocates storage and configures access rights. An MPU checks regions; an MMU can also translate addresses. Diagnosis can read a shared sample buffer and write its own state.
Stack guard Denies access to a guard region or page so a crossing access faults. A stack write into the guard triggers a protection fault.
Stack monitoring Checks stack usage or a sentinel at defined points. A context-switch check can detect an overrun after it has occurred.

Distinguish enforcing an access boundary from checking whether a stack stayed within its budget.

MPU: Memory Protection Unit. MMU: Memory Management Unit. See AUTOSAR OS R24-11, §§7.5 and 7.7.

Timing Protection in AUTOSAR OS

A memory-isolated diagnostic component can still consume CPU time, hold a lock or trigger too often.

Configured limit What the OS monitors Motor example
Execution Budget CPU time used by a task or Category 2 ISR Diagnosis exceeds its allowed execution.
Lock Budget Time holding a resource or keeping interrupts suspended Diagnosis delays the next control release or dispatch.
Time Frame Minimum spacing of monitored task activations/releases or Category 2 ISR arrivals A diagnostic source triggers too frequently.

Timing protection enforces assumptions at runtime. Schedulability analysis checks whether those assumptions suffice for the deadlines.

Availability and handling depend on configuration. AUTOSAR OS R24-11, §§7.7.2, 7.8 and 7.11.

The Same Completion Takes Different Paths

The controller waits for a DMA completion. Compare what the configured architecture has to do.

Illustrative design Completion path What enters the timing argument?
Linked services Interrupt handler publishes completion to the linked control code. Interrupt delay, handler work and the next allowed dispatch.
Monolithic kernel Kernel driver signals a waiting application context. Kernel wake-up path and any context or protection-domain switch.
Microkernel with driver service IRQ notification reaches the service, which signals the controller via IPC. Driver-service scheduling, message delivery and dispatch across domains.

Compare concrete paths and their bounds. Architecture labels alone give no runtime cost.

Account for the Time Used by the Runtime

The control computation can consume up to 0.55 ms of its 1.0 ms software deadline.

Where time is spent What the timing argument must cover
Before the software release Interrupt delivery and notification if they lie in this part of the end-to-end chain
From release to finish Time when other work runs, kernel paths, and dispatch costs attributable to the interval
Inside the control computation Execution-time bound for the code, with memory and cache assumptions stated

A bound is useful only if its interval and assumptions match the budget.

In this example, the CPU computation leaves 0.45 ms for everything else between release and finish in its worst execution case.

OSEK/VDX Alarm and Task Activation

How can the drive configure a periodic control activation at build time?

Configured object Selected properties Runtime effect
Counter Driven by the system time base Provides ticks for the alarm
Cyclic alarm Action: activate Control Requests a task activation on expiry
Basic task Control Fixed priority, SCHEDULE = FULL Eligible for preemptive dispatch, terminates after the control step

The configuration specifies what becomes ready; the scheduler still chooses what runs.

OSEK/VDX OS 2.2.3, §§4.2, 4.5–4.6 and 9. Selected settings for an illustrative configuration.

OSEK/VDX Basic and Extended Tasks

The periodic control step can finish after each activation. A diagnostic task may wait for a device event.

Basic task Extended task
Activation Becomes ready Becomes ready
Event wait No Waiting state WaitEvent may enter Waiting
End of activation TerminateTask TerminateTask
Preemption Depends on scheduling configuration Depends on scheduling configuration

Task type controls event waiting; scheduling configuration controls task preemption.

A Shared Buffer Can Delay a Job

The controller and the diagnostic thread access the same published sample.

  1. The diagnostic thread holds the mutex protecting the sample.
  2. The controller becomes ready and is dispatched.
  3. Its attempt to acquire the mutex waits until the resource is available.

A ready job can start on time and then block on a resource.

Chapter Map: Task Model and Schedulability

5.1 Timing RequirementsFrom plant timing to firmware scheduling
5.2 Scheduling ImplementationsPeriodic loop, schedule table and online selection
5.3 Execution ModelsSwitch points and activation lifecycles
5.4 RTOS Requirements and ArchitectureAUTOSAR, kernel designs, protection and OSEK/VDX
5.5 Task Model and SchedulabilityTask tuples, jobs and timing guarantees

Describe the workload and ask what guarantees can be proved.

One Task, Successive Jobs

The design defines one recurring control task. Each timer release requests one concrete invocation.

images/05-rtos/task-jobs.svg
One persistent task specification above a time axis with three releases, each creating a distinct job

A task is the recurring specification. A job is the instance the scheduler plans.

The Periodic Task Tuple

The three timing quantities from the motor example now become model parameters.

\[ \tau_i=(T_i,C_i,D_i,\phi_i) \]

Symbol Meaning Control example, \(i=1\)
\(\tau_i\) Task with index \(i\) Control computation
\(T_i\) Period between nominal releases \(2\,\mathrm{ms}\)
\(C_i\) Upper bound on execution time per job \(0.55\,\mathrm{ms}\)
\(D_i\) Relative deadline from release \(1.0\,\mathrm{ms}\)
\(\phi_i\) Nominal first release on the chosen time axis \(0\,\mathrm{ms}\) on a release-aligned axis

The tuple describes the task as a whole; each release gives an instance its own time coordinates.

\(\phi_i\) is a course convention for the phase.

From the Task Tuple to an Individual Job

\(J_{i,k}\) is job \(k\) of task \(\tau_i\). The job index \(k=1,2,\ldots\) counts releases of that task.

Job property In the periodic model without release jitter
Release \(r_{i,k}\) \(\phi_i+(k-1)T_i\)
CPU demand bound Each job may require up to \(C_i\) of CPU time.
Absolute deadline \(d_{i,k}\) \(r_{i,k}+D_i\)
Actual finish \(f_{i,k}\) Determined by the execution and schedule.

The release and the relative deadline give the job a specific deadline on the time axis.

For the control task, the second job becomes ready at 2 ms and must finish by 3 ms.

Execution Time and Response Time

Job \(k\) of task \(i\) can wait before its first dispatch and again after preemption.

images/05-rtos/job-timeline.svg
Release, two execution intervals separated by preemption, finish and absolute deadline

Execution time adds the two running intervals. Response time is \(f_{i,k}-r_{i,k}\).

The job meets its deadline if \(f_{i,k}\le d_{i,k}\). The task’s worst-case response time is \(R_i\).

When One Activation Has Several Dependent Steps

A sample may require filtering before torque calculation and limit checking can use the result.

images/05-rtos/dag-extension.svg
One activation instantiates a directed acyclic graph; filter precedes torque calculation and limit checking, and their completion precedes publication

A directed acyclic graph (DAG) models these dependencies explicitly. Its successors become eligible after their prerequisites.

Extension of the model. The first scheduling analyses use one independent sequential job per release.

Periodic, Sporadic and Aperiodic Work

The controller must describe how often each kind of work can arrive.

images/05-rtos/arrivals.svg
Periodic control arrivals, irregular fault notifications with a minimum separation, and aperiodic service requests without a guaranteed minimum gap

The arrival model determines which workloads the timing claim covers.

Sporadic Tasks and Aperiodic Jobs

The control loop has a period. For other work, the arrival guarantee changes.

Workload Model in this course
Periodic \(\tau_i=(T_i,C_i,D_i,\phi_i)\). The period gives nominal release times.
Sporadic \(\tau_i=(T_i,C_i,D_i)\). Here \(T_i\) gives a minimum inter-arrival time.
Aperiodic The workload has no guaranteed minimum inter-arrival time in this model. For a given set of jobs, specify individual releases, demands and deadlines.

The same \(T_i\) symbol describes a different arrival guarantee in the periodic and sporadic models.

Arrival, Release and First Dispatch

A physical event can occur before the software is ready to process it.

images/05-rtos/release-jitter.svg
Distinct time intervals from nominal arrival to release, from release to first execution, and from release to finish

\(J_i\) bounds release jitter. Waiting for the CPU after release contributes to response time.

EZS Cheat Sheet · Tasks and Jobs

\(i\) identifies a task. \(k=1,2,\ldots\) counts its successive jobs.

Task notation Meaning Job notation Meaning
\(\tau_i\) Task \(i\) \(J_{i,k}\) Job \(k\) of task \(i\)
\(T_i\) Period or minimum inter-arrival time \(r_{i,k}\) Release time
\(C_i\) Execution-time bound per job \(d_{i,k}=r_{i,k}+D_i\) Absolute deadline
\(D_i\) Relative deadline \(f_{i,k}\) Finish time
\(\phi_i\) Phase of a periodic task \(f_{i,k}-r_{i,k}\) Actual response time
\(J_i\) Release jitter bound \(f_{i,k}\le d_{i,k}\) Deadline met
\(R_i\) Worst-case response time

Periodic \(\tau_i=(T_i,C_i,D_i,\phi_i)\) · Sporadic \(\tau_i=(T_i,C_i,D_i)\)

Burns Standard Notation (Davis, 2013). Course conventions \(\phi_i\), \(J_{i,k}\), \(r_{i,k}\) and \(f_{i,k}\).

The First Scheduling Model

The complete drive includes device waits, shared buffers and an actuator. Which part can we analyse first?

Assumption for the initial analysis Implication
One CPU At most one job executes at a time.
Independent CPU jobs There are no precedence or shared-lock constraints in this model.
No self-suspension Once released, a job stays eligible until it finishes.
Specified workload and costs Arrival assumptions, execution bounds and deadlines delimit the claim.

Analyse the CPU workload under explicit assumptions.

From One Schedule to a Guarantee

A single trace shows that both jobs met their deadlines in one situation.

Question Scope
Feasibility Does a schedule satisfying all constraints exist for this job set?
Schedulability under a policy Will the specified policy meet the deadlines for every workload allowed by the model?
Evidence Use a test whose assumptions match the claim.

A trace can demonstrate a miss. A guarantee must cover all admitted cases.

Reading a Schedulability Test

A test condition is evaluated for a specified workload model and policy.

Test condition If it holds If it fails
Necessary The result may remain open. The guarantee fails.
Sufficient The guarantee holds. The result may remain open.
Exact The guarantee holds. The guarantee fails.

Check the direction of implication before using a test result.

Self Check

The device completes a transfer while another job runs. A diagnostic thread is also ready.

  1. Which transition is caused by the ISR, and when does the controller use the CPU again?
  2. Which parts of the trace count toward execution time and which toward response time?
  3. Which workload and policy assumptions would you need to justify a hard deadline?

Identify the release or wake-up, dispatch and finish before making a timing claim.

Scheduling Problems Ahead

The first analysis considers independent jobs on one CPU.

Next topic Question
Aperiodic jobs Can the given jobs meet their deadlines?
Periodic tasks and EDF How do recurring arrivals affect deadline guarantees?
Fixed-priority scheduling How much delay can higher-priority work impose?
Shared resources and blocking How much delay can a resource holder impose?

The task model carries across these questions as we add new assumptions.

References

Reading in Marwedel, 4th edition

  • Embedded and real-time operating systems → §§4.1.1–4.1.2
  • Scheduling problem and assumptions → §§6.1.1–6.1.2
  • Follow-up reading → §§6.2.1 and 6.2.3 (one CPU), §4.2 (resource protocols)